This 4-story + penthouse project with approximately 36 units is under construction as by-right under existing zoning. There is no available completion date.
August 2021: Raze permit to demolish existing buildings applied for.
December 2021: Public space permit submitted.
April 2022: Raze permit issued.
June 2022: Public space permit issued.
February 2023: Razing of existing buildings begins.
May 2024: Inspection to address sinkhole from gas line and collapsed fencing. Issues remediated.
August 2024: Plumbing permit issued.
February 2025: Stop work order to address public space issues. Stop work order lifted following remediation.
July 2025: Tax sale.